Our planning application for Q1 was approved by Boston Borough Council on 5th August 2014.

The application was referred to the Secretary of State who had 21 days (plus a slight extension) to decide whether or not to ‘call in’ the application to determine it himself. He decided not to call in the application, and so the decision was referred back to the Borough Council. Therefore, once the Section 106 legal agreement had been signed, planning permission was formally granted for Q1 on 30th March 2015, in line with the decision made by the planning committee.

Subject to securing appropriate funding, work could then start on the Community Stadium and access later in 2015, or in 2016. Detailed applications for the residential and commercial elements of the project will also be brought forward in phases at a later date.